News Flash

Posted on: July 26, 2018

July 26, 2018 Construction Update

The Roadway has been paved and striped and construction is nearing completion with the installation of landscaping and irrigation, street lights and pedestrian guardrail currently in progress.

A ribbon-cutting ceremony and opening of the Roadway to the Pub...

Read on...

Harbor Hill Drive Extension
Posted on: April 10, 2018

April 10, 2018 Construction Update

Please contact Construction Supervisor Kyle Neiman at 253-377-1378 for additional information.

Harbor Hill Drive Extension
Posted on: February 21, 2018

February 21, 2018 Construction Update

This road closure will allow for the construction of a new roundabout at the Harbor Hill Dr. and Sentinel Dr. intersection. 

The road closure will begin on March 19th and will be in effect through April 17, 2018. No local access will be provided t...

Read on...

Harbor Hill Drive Extension
Posted on: December 14, 2017

December 14, 2017 Construction Update

The roadway alignment on Burnham Drive will be modified at the new Harbor Hill Drive extension area in order to shift traffic to the east through the construction zone, and allow for the construction of a new retaining wall, roadway fill and completion of...

Read on...

Harbor Hill Drive Extension
Posted on: November 1, 2017

November 1, 2017 Construction Update

The general roadway grade has been established from Burnham Drive to Harbor Hill. The stormwater detention pond is complete as well as the majority of the soldier pile walls. The Sportsman’s Club new driveway is paved.

Harbor Hill Drive Extension