Work in Progress:
Construction of the boat storage building is underway. Most of the structural work is complete and the majority of the work is now taking place inside the building and on the roof. Interior Sheetrocking of the boat storage is complete and crews are working on the interior finishes.
Construction the Ancich and Jerkovich Piers continues to go well. Timber decking installation is complete. The Jerkovich Pier catwalk is installed.
Impacts to the Public:
Pedestrian Detour Route
Quigg has closed the parking stalls and sidewalk directly adjacent to the site for the duration of the project. Pedestrian foot traffic is no longer permitted to use the sidewalk directly in front of the site. However, a pedestrian detour is established. The pedestrian route shifts foot traffic from the sidewalk on the north side of Harborview Drive to the sidewalk on the south side of Harborview drive, from Harborview/Stinson to Harborview/Novak. There are established pedestrian crossings in both locations. A temporary rectangular rapid flashing beacon (RRFB) is installed at the Harborview/Stinson crosswalk.
Harborview Drive Impacts Harborview Drive will be operating as a two-lane, two-direction street for the foreseeable future. However, please use caution as trucks are currently entering/leaving the site hauling excavation material. There will be access to all businesses and residents for the duration of the project.
Ancich sidewalk improvement and associated frontage improvement construction is expected to be completed over the next month. The offsite sidewalk improvements are constructed along Harborview Drive. They begin at Novak Street and continue to Eddon Boat Park. The contractor is expected to begin removal and replacement of private driveway approaches over the next month. The project timeline will be updated on the project website as information becomes available. Thank you for your patience.
Noise Impacts
Night work is not anticipated for the foreseeable future.
Remaining Work and Timelines:
September/October: Private driveway approach removal and replacement, geofoam installation on boat storage building deck, boat storage building interior finishes, planter box walls on boat storage building roof, construction of west side retaining walls, installation of netshed doors and windows, completion of sidewalk frontage improvements.
DOWNTOWN GIG HARBOR IS OPEN FOR BUSINESS DURING CONSTRUCTION
PLEASE SUPPORT LOCAL BUSINESSES
ACCESS TO BUSINESSES and RESIDENCES WILL BE MAINTAINED AT ALL TIMES.