Ancich Waterfront Park Construction Update 9-17-18

 

ANCICH PARK AND NETSHED REHABILITATION PROJECT

 

PROJECT UPDATE 9/17/18


 

Ancich Waterfront Park has been under construction since January 2018 and has approximately three months left of work until completion.  The project continues to be on-time and within the originally adopted budget, with approximately 40% of the project budget remaining.  

Work in Progress: 

Construction of the boat storage building is underway. Most of the structural work is complete and the majority of the work is now taking place inside the building and on the roof. Interior Sheetrocking of the boat storage is complete and crews are working on the interior finishes.

 

Construction the Ancich and Jerkovich Piers continues to go well. Timber decking installation is complete. The Jerkovich Pier catwalk is installed.

 

Impacts to the Public:

 

Pedestrian Detour Route

 

Quigg has closed the parking stalls and sidewalk directly adjacent to the site for the duration of the project. Pedestrian foot traffic is no longer permitted to use the sidewalk directly in front of the site. However, a pedestrian detour is established. The pedestrian route shifts foot traffic from the sidewalk on the north side of Harborview Drive to the sidewalk on the south side of Harborview drive, from Harborview/Stinson to Harborview/Novak. There are established pedestrian crossings in both locations. A temporary rectangular rapid flashing beacon (RRFB) is installed at the Harborview/Stinson crosswalk.


 Harborview Drive Impacts 

Harborview Drive will be operating as a two-lane, two-direction street for the foreseeable future. However, please use caution as trucks are currently entering/leaving the site hauling excavation material. There will be access to all businesses and residents for the duration of the project.

 

Ancich sidewalk improvement and associated frontage improvement construction is expected to be completed over the next month. The offsite sidewalk improvements are constructed along Harborview Drive. They begin at Novak Street and continue to Eddon Boat Park. The contractor is expected to begin removal and replacement of private driveway approaches over the next month. The project timeline will be updated on the project website as information becomes available. Thank you for your patience.

 

Noise Impacts

 

Night work is not anticipated for the foreseeable future.

 

Remaining Work and Timelines:

 


September/October:  Private driveway approach removal and replacement, geofoam installation on boat storage building deck, boat storage building interior finishes, planter box walls on boat storage building roof, construction of west side retaining walls, installation of netshed doors and windows, completion of sidewalk frontage improvements.

 


 

 

 

 

 

 

 

DOWNTOWN GIG HARBOR IS OPEN FOR BUSINESS DURING CONSTRUCTION  
PLEASE SUPPORT LOCAL BUSINESSES

 

ACCESS TO BUSINESSES and RESIDENCES WILL BE MAINTAINED AT ALL TIMES.

 

Primary project contact:
George Flanigan, Construction Supervisor
Flanigang@cityofgigharbor.net or (253) 853-7695

 

Project Updates:
These project updates will be posted on the City’s web site at www.cityofgigharbor.net/574/Ancich-Waterfront-Park

 

The City will circulate periodic updates by email. If you know someone that would be interested in receiving these email notices, please contact Maree George at  georgem@cityofgigharbor.net or 253-853-7553 and indicate that you wish to be added to the stakeholders list for the Ancich Waterfront Park and Netshed Restoration project.

 