  1. April 10, 2018 Construction Update

    April 10, 2018 Construction Update Due to unforeseen construction delays as a result of adverse weather, the City will be extending the duration of the road closure at the Harbor Hill Drive and Sentinel Drive intersection until April 23, 2018. Read on...
  2. February 21, 2018 Construction Update

    The City's Harbor Hill Extension Project, extending Harbor Hill Dr. to Burnham Dr. has been under construction since July 2017. In order to complete this project, there will be a 1-month road closure of Sentinel Dr. where it connects to Harbor Hill Dr. Read on...
  3. December 14, 2017 Construction Update

    Roadway alignment modification on Burnham Drive to begin December 18. Read on...
View All

Project Description

Construct a new roadway including two roundabouts, sidewalks, curb and gutter, fencing and structural earth walls, soil nail wall, soldier pile walls, a cast in place wall/barrier and a ballistic wall that will connect Harbor Hill Drive to Burnham Drive. Work also includes the construction of a stormwater pond, illumination system, utility work and relocation and landscaping.  Please expect ongoing delays motorists.      

Click here for new roadway alignment.           

Project Schedule

Construction began on July 24, 2017.  Completion date is anticipated for December  2018.    

  1. Trent Ward

    Senior Engineer
    Phone: 253-853-7637

  2. Kyle Neiman

    Construction Supervisor
    Phone: 253-853-7607

  3. Maree' George

    Administrative Assistant